Client
SASAD
Period :
1990 Nov - 1991 Nov
Location :
Iran
Type of Project :
EPC
In October 1990 OMRAB conclusion a contract for engineering, procurement, construction of Chamran complex sanitary waste water treatment plant. This project accomplished this project during two years.
Scope of woks includes procurement and installation of mechanical, electrical, instrumentation and control (I&C) equipment and construction of water treatment plant with total capacity of 26,000 Cu.m per day.
The treatment process has been designed base on a conventional treatment system includes flash mixing unit, flocculation unit, sedimentation unit, gravity rapid sand filter, gas chlorination and control system.
In this project most of hydro electromechanical equipment supply from west of Europe well known partners and suppliers such as Endress Hauser, Siemens, Mouell, Alldos (Germany), Hibon (France)